Ground Floor Slab Work

construction Progress

Overall Construction Progress 37%

Based on our internal inspection carried out on JULY-2026, the overall construction progress has reached 37%.

JULY 2026

concrete Pouring

Structural work of the 3 Basement Levels and the Lower Ground has been successfully completed. Block masonry work and electrical wiring on these levels are in progress. The pouring of columns, shear walls, and lift walls for the Ground Floor has been completed. Formwork for the Ground Floor slab is currently in progress, with approximately 50% completed to date.