Cloud Tower 1

construction Progress

October 2026

The excavation of our 52,000 sq. ft. plot is 100% complete, reaching 60 ft. below road level. We have conducted two successful pile load tests using 1,280 tons and 1,920 tons.

Furthermore, we’ve completed 246 foundation piles, each extending 120 ft. deep to support the structure & in this process 270 ton of steel and 3500 m³ concrete was poured.

Cloud Residences

construction Progress

October 2026

45% of total structural work has been completed including excavation, foundation raft, 3 basements, lower ground, ground and first floor’s slab along with lighting and block masonry work of all 3 basements and lower ground.

At the moment reinforcement work of columns of 2nd floor slab (7th slab) is completed while Scaffolding & Form-work of 7th slab is scheduled for Nov 2026.

Our Events

Karachi Road Show

15 August 2026

Karachi Road Show

08 August 2026

Calgary Road Show

05 July 2026

New York Road Show

12 July 2026

Islamabad Road Show

18 & 19 April 2026

The Torch Doha

10 Jan 2026