Foundation lean Work

construction Progress

In lean Process 30%

Based on our internal inspection carried out in October-2026, the overall lean progress has reached 30%.

October 2026

Cloud Tower-1 Construction Update

The excavation of our 52,000 sq. ft. plot is 100% complete, reaching 60 ft. below road level. We have conducted two successful pile load tests using 1,280 tons and 1,920 tons of load. Furthermore, we’ve completed 246 foundation piles, each extending 120 ft. deep to support the structure & in this process 270 ton of steel and 3500 m³ concrete was poured.

With the lean concrete in progress, we’ve now moved on to raft foundation work.